List of Para (Order by Subject)
  View Detailed Audit Report
Department :Irrigation & Flood Control
Sub department:E.E., Flood Control Division-II (I & F.C.D.), Sector-15, Rohini, New Delhi (1404/12)
S No. Start Year End Year Para No. Sub Para Subject Status* Outstanding Amount (in Rs.)
1 2025 2026 2 1 (A) Blockage of funds amounting to Rs. 125.73 Lakh due to Non completion of work O 0
2 2025 2026 2 2 (B) Slow progress of works leading to missing the deadline for completion of works O 0
3 2023 2025 8 Abnormal delay in deposit of Labour Cess O 0
4 1976 2002 5 Analysis of Work O 0
5 1976 2002 8 Analysis of Work O 0
6 2023 2025 2 Award of work abnormally below estimated cost O 0
7 1976 2002 20 Balance work of construction of Bridge on procky foundation with single span of 95 O 0
8 2010 2012 1 Construction of RCC retaining wall between RD 21650m to RD 21450m and providing CC title O 0
9 1976 2002 10 Contractor ledger O 0
10 1976 2002 22 Contractor ledger O 0
11 1976 2002 27 Contractor ledger O 0
12 1976 2002 41 Contractor ledger O 0
13 2023 2025 15 Delay in depositing government money in government account O 0
14 2019 2023 11 Difference in payment between tender amount and gross work amount O 0
15 2019 2023 3 Excess payment on account of LTC Special Cash Package Scheme O 6000
16 2016 2019 1 Inaccurate estimates and execution of extra work without taking competitive rates O 0
17 2023 2025 10 Inclusion the name of major son in DGEHS Medical Card O 0
18 1976 2002 12 Income Tax Calculation of Sh. Naresh Mohan, A.E O 0
19 2013 2016 6 Income Tax for the FY 2013-14, 2014-15 & 2015-16 O 0
20 1976 2002 2 Infructuous expenditure due to collapse of steel truss Bridge near Timar Pur. O 0
21 2006 2008 46 Infrutious expenditure of Rs. 13333/- on Advertisement O 0
22 2023 2025 16 Irregular contingent expenditure made by the Division and charged to work O 0
23 2019 2023 14 Irregular expenditure of Rs. 1.39 lakh in violation of conditions of the contract O 0
24 2025 2026 7 Irregular purchase of Rs. 1394478/- (Non procurement of services through GeM) O 0
25 1976 2002 35 Liveries account O 0
26 1976 2002 31 Local purchase O 0
27 1976 2002 38 Log book O 0
28 1976 2002 14 Log book O 0
29 2025 2026 5 Loss of Govt. Infrastructure and wastage of time due to foreclosure of work. O 0
30 2013 2016 7 Loss of Rs. 46454 due to non-availing of 15% commission on advertisement O 46454
31 1976 2002 32 M.B. Register Vol.II O 0
32 1976 2002 19 Manufacturing and supply of C.C.Tiles of 300X300X50 MM size at Bharat Nagar Tile Factory O 0
33 1976 2002 29 Muster Rolls O 0
34 2019 2023 15 Non deduction of TDS on GST O 68347
35 2023 2025 5 Non deduction of TDS on professional fees O 345972
36 2019 2023 8 Non deduction of the amount of Labour Cess O 3501
37 2023 2025 6 Non procurement of services through GeM O 0
38 2025 2026 8 Non production of records. O 0
39 2019 2023 12 Non refund/revalidation of FDR/Bank Guarantees O 0
40 2025 2026 6 Non registration of construction workers. O 0
41 2025 2026 3 Non revalidation of FDR/Bank Guarantee. O 0
42 2016 2019 6 Non revalidation of FDR/Bank Guarantees O 0
43 2023 2025 14 Non revalidation of FDR/Bank Guarantees O 0
44 2010 2012 3 Non-adherence of the provision of CPWD Manual O 0
45 2008 2010 3 Non-completion of Bridge work in time related to Common Wealth Games O 0
46 2023 2025 4 Non-completion of projects O 0
47 2023 2025 7 NPR O 0
48 2016 2019 5 Office expenditure charged to work O 0
49 2019 2023 9 Office expenditure charged to works O 0
50 1976 2002 7 Outstanding in Register of Misc. P.W.advances O 0
51 2023 2025 13 Payment of final bills not made within time limit prescribed in CPWD manual O 0
52 2019 2023 13 Payment without obtaining the approval of Deviation Statement O 0
53 2010 2012 9 Physical verification of T&P, MAS Account O 0
54 2008 2010 5 POL Register and Log Book O 0
55 1976 2002 15 Providing outfall structure at Mukherjee Nagar S.W.P.Sintion O 0
56 2025 2026 1 Public works deposit O 0
57 1976 2002 36 Purchase of T&P excess over Rs.5000/- O 0
58 1976 2002 9 Recovery of telephone charged from Sh. Kishan Chand Ex.Er. O 0
59 2013 2016 1 Recovery of Value Added Tax (TDS) amounting to Rs. 1823391/- O 1823391
60 1976 2002 21 Register of Misc.P.W.advance O 0
61 1976 2002 33 Register of review of M.B by Divisional accountant O 0
62 1976 2002 34 Register of work O 0
63 1976 2002 6 Register of work O 0
64 1976 2002 18 Remodelling and linning of Najafgarh drain from R/O 136540 to 136700 D/S Ambala Railway Bridge O 0
65 1976 2002 24 Restoration of bank o N.G.Drain SH strenghing of left bank of N.G.Drain O 0
66 1976 2002 16 Restoring right bank of Najafgarh drain at R.D 150000 O 0
67 2016 2019 2 Revised Technical Sanction O 0
68 2019 2023 16 Short deduction of Income Tax (TDS) under Section 194 J O 75302
69 2013 2016 2 Short deduction of Income Tax (TDS) under section 194 J amounting to Rs. 221280/- O 221280
70 2013 2016 4 Short Recovery amounting to Rs. 21420/- of monthly subscription and insurance cover O 21420
71 2010 2012 6 Short Recovery of DHS for regular staff (Rs. 17960/-) & Work Charge Staff (Rs. 30,680/-) O 4680
72 2013 2016 5 Short Recovery of License Fee amounting to Rs. 1440/- O 760
73 1976 2002 3 Short supply of cement O 0
74 2019 2023 10 Slow progress of work leading to missing the deadlines for completion of work O 0
75 2016 2019 3 Slow progress of work leading to missing the deadlines for completion of work O 0
76 2023 2025 3 Slow progress of works leading to missing the deadlines for completion of work O 0
77 1976 2002 43 Stock Register O 0
78 1976 2002 25 Strengthing of Right Bank of N.C.Drain (old alignment) RD 150,000/ to rail regulator O 0
79 1976 2002 13 Telephone Charges O 0
80 1976 2002 4 Theft of store due to ineffective vigilance Rs.2328/- O 0
81 2016 2019 10 Time Barred Cheque amounting to Rs. 3200/- O 0
82 2023 2025 7 Un-fruitful expenditure due to foreclosure of works O 0
83 2008 2010 2 Un-fruitful expenditure of Rs. 59.32 lakhs O 0
84 2010 2012 4 Undue benefit to contractor amounting to Rs. 87,290/- providing Safeda allies and EC Bags O 0
85 2019 2023 7 Unfruitful expenditure of Rs. 110.93 lakh due to work held/stopped by the contractor O 0
86 2006 2008 45 Unfruitful Expenditure of Rs. 5234430/- O 0
87 2010 2012 2 Unfruitful expenditure of Rs. 79,679/- on advertisement O 0
88 2019 2023 4 Unfruitful expenditure of Rs. 90.73 lakh due to foreclosure of work O 0
89 2008 2010 4 Violation of Agreement Clauses O 0
90 2023 2025 12 Withheld amount due to non-submission of 3rd party report O 0
91 2019 2023 6 Withheld the amount for non approval of extension of time O 0
92 1976 2002 40 Work charge vouchers O 0
93 2016 2019 4 Work completed but final payment has not been made O 0
94 2025 2026 4 Work held up due to non-availability of clear site. O 0
* NOTE:
'O'- Outstanding Paras.
'R' -Reply submitted by the Department/Units.
'C'- Comment by the Directorate of Audit on reply submitted.