1 2019 2023 5 Abnormal delay in completion of works beyond the stipulated date of completion O 0
2 2019 2023 2 Abnormal difference between estimated cost and quoted tendered cost in civil works O 0
3 2016 2019 13 Amount withheld on account of GST O 0
4 2023 2025 2 Award of work on a below rates in comparison to the Estimated cost O 0
5 2019 2023 6 Discrepancies in work of Relaying of "World Athletics" approved 400 mtr Synthetic Athletic Track O 0
6 2019 2023 1 Escalation in cost of work due to unrealistic estimates O 0
7 2013 2016 4 Expenditure on the work had been doen more than the limit prescribed in CPWD Manual Clause 2.3.5. O 0
8 2006 2007 3 Final Settlement to contractor without obtaining completion certificate from DCP (NW). O 0
9 2016 2019 9 Hiring of vehicles through work under during the period 2016-19 O 0
10 2016 2019 12 Huge deviation between awarded amount and actual expenditure incurred on construction work O 0
11 2023 2025 6 Inadmissible payment of Rs. 9815468 in violation of the provisions of CPWD manual O 9815468
12 2013 2016 3 Inappropriate Estimates O 0
13 2008 2010 2 Inappropriate Estimates O 0
14 2016 2019 7 Irregular expenditure on deployement of contractual staff in division office without approval O 0
15 2016 2019 10 Irregular purchase of furniture/photocopier amounting to Rs. 277971/- O 0
16 2005 2006 1 Irregularities in Procurement of Material for day Maintenance Work Vide Agreement No. 28. O 0
17 2023 2025 11 Late deposit of labour cess with the Delhi buildings and other construction Rs. 51.11 lakhs O 0
18 2013 2016 5 Misutilization of Imprest amount O 0
19 2008 2010 4 Name of the Work - EOR to Misc. Work at DGHS Block, Ashok Vihar, Delhi O 0
20 2008 2010 1 Name of the Work - EOR to Rajkiya Pratibha Vikas Vidyalaya, Kishan Ganj, Delhi O 0
21 2023 2025 8 Non levy of compensation in delayed work Rs. 2895010 O 0
22 2023 2025 10 Non recovery of Rs. 2.10 lakh for non-deployment of graduate engineer/technical O 0
23 2023 2025 3 Non revalidation/release of FDR/bank Guarantees O 0
24 2023 2025 12 NPR O 0
25 2023 2025 4 Performance/output of the Division O 0
26 2023 2025 1 Public works - Civil Deposits O 0
27 2008 2010 8 Purchase of Furniture O 0
28 2008 2010 7 Purchase of Stationery Items O 0
29 2016 2019 5 Recovery of Rs. 243326/- on a/c of loss of discount due towarding contract to private agency O 243326
30 2008 2010 5 Renovation of Garage No. 5 & 6 of School Health Centre for use of VRFC O 0
31 2008 2010 3 Repetition of Extra Items O 0
32 2023 2025 5 Slow progress of works leading to missing the deadlines for completion of work O 0
33 2013 2016 7 Stationary Purchases O 0
34 2013 2016 1 Undue advantage to contractor O 0
35 2023 2025 7 Undue benefit given to the Contractor O 0
36 2019 2023 4 Unfruitful expenditure of Rs. 1.60 Crore on the work of "Extra Ordinary Repair to Police Colony O 0
37 2023 2025 9 Unfruitful expenditure of Rs. 22.48 lakhs due to foreclosure of work O 0
38 2005 2006 2 Unjustified Deviation / Extra items Huge Payments to Contractors. O 0
39 2016 2019 8 Unnecessary expenditure of Rs. 114.43 lakhs on outsource labourers O 0
40 2013 2016 2 Work Order O 0
41 2008 2010 6 Work Order O 0