Webstyle produced NavBar
List of Para (Order by Subject)
  View Detailed Audit Report
Department :Public Works (PWD)
Sub department:(F-13) Flyover Project Divi., Mukarba Chowk, GT Karnal Road, Delhi (1996/12)
S No. Start Year End Year Para No. Sub Para Subject Status* Outstanding Amount (in Rs.)
1 2016 2019 5 Amount witheld on account of GST/EOT/Milestone O 0
2 2019 2023 9 Amount withheld on a/c for submission of Test Report and Completion Plan O 0
3 2019 2023 2 Avoidable Payment - 13.01 Lakh O 0
4 2016 2019 4 Excess consumption of petrol beyond the prescribed limit on staff cars O 0
5 2016 2019 11 Expenditure on inauguration ceremonies conducted during 2016-2019 O 0
6 2016 2019 8 Hiring of vehicles through work under during the period 2016-2019 O 0
7 2016 2019 6 Irregular contingent expenditure made by the division and charged to work O 0
8 2016 2019 10 Irregular execution of works through work orders O 0
9 2016 2019 9 Irregular expenditure on deployment of contractual staff in division office without approval O 0
10 2007 2012 2 Irregular payment of Rs. 99,86,625/- to the contractor for providing barricading O 0
11 2016 2019 12 Irregular procurement of petty items O 0
12 2016 2019 7 Maintaining and updating website of purchase of IT items O 0
13 2019 2023 3 Non ajustment of Mobilization advances worth Rs. 20000000/- O 0
14 2016 2019 15 Non production of Records O 0
15 2019 2023 10 Non production of Records O 0
16 2016 2019 2 Non revalidation of FDR/Bank Guarantees O 0
17 2019 2023 4 Non revalidation of FDR/BG O 0
18 2019 2023 6 Non-Association of Account Functionaries in the purchase file/Work file/Supply Order O 0
19 2019 2023 5 Pending Arbitration Cases O 0
20 2016 2019 14 Performance/output & non imposition of penalty on account of delay in completion of work O 0
21 2019 2023 1 Public Works Deposit O 0
22 2019 2023 8 Time Barred cheques amounting to Rs. 34664378/- O 0
23 2016 2019 13 Unauthroized payment towards the maintenance of the Vehicle No. DL-1CP-2251 (Ambassador) O 0
24 2019 2023 7 Unfruitful expenditure of Rs. 49406540/- due to non completion of work due to supply O 0
* NOTE:
'O'- Outstanding Paras.
'R' -Reply submitted by the Department/Units.
'C'- Comment by the Directorate of Audit on reply submitted.