Webstyle produced NavBar
List of Para (Order by Outstanding Amount)
  View Detailed Audit Report
Department :Delhi Jal Board
Sub department:Executive Engineer, (SDW)-III, Delhi Jal Board, STP Yamuna Vihar, Delhi
S No. Start Year End Year Para No. Sub Para Subject Status* Outstanding Amount (in Rs.)
1 2022 2024 1 Short Recovery of TDS of Rs.102774/- O 102774
2 2022 2024 2 Shortcomings in Construction of 3.85 (MGD) WWPS including rising main at Harsh Vihar. O 0
3 2022 2024 3 Award of work at abnormally below the Estimated Cost. O 0
4 2022 2024 4 Non-obtaining of Performance Security amounting to Rs. 85,196/- from the contractor. O 0
5 2022 2024 5 Non-maintenance of Cash Book for financial year 2022-23 & 2023-24. O 0
6 2022 2024 6 Discrepancies/shortcomings in the work of 10 MGD STP Ph-II, Yamuna Vihar, under AMRUT Scheme. O 0
7 2022 2024 7 Non-surrender of savings. O 0
8 2022 2024 8 Shortcomings in the work along with other associated/allied appurtenant work on Design Build. O 0
9 2022 2024 9 Non-production of records. O 0
* NOTE:
'O'- Outstanding Paras.
'R' -Reply submitted by the Department/Units.
'C'- Comment by the Directorate of Audit on reply submitted.