List of Para (Order by Outstanding Amount)
View Detailed Audit Report
Department :
Local Fund Accounts (LFA)- Delhi Jal Board
Sub department:
Executive Engineer (EAP)-III, Delhi Jal Board, Over Head Tank, Ashok Vihar, Delhi-110052
S No.
Start Year
End Year
Para No.
Sub Para
Subject
Status*
Outstanding Amount (in Rs.)
1
2023
2024
1
Short recovery of Compensation charges/Liquidated damages amounting to ₹2533.90 lakhs.
O
0
2
2023
2024
2
Shortcoming in execution of work.
O
0
3
2023
2024
3
Discrepancies in opening / closing balances of Bank Accounts operated in the Division.
O
0
4
2023
2024
4
Loss of ₹20867/- on account of not availing 15% Rebate on Advertisements.
O
0
5
2022
2023
1
Loss due to not availing 15% rebate on advertisement
O
0
6
2022
2023
2
Transfer of ongoing work/project to the other division
O
0
7
2022
2023
3
Discrepancies in work
O
0
8
2022
2023
4
Release of payments without compliance of agreement
O
0
9
2024
2025
1
Unfruitful expenditure amounting to Rs. 120.76 crore due to non availability of raw water for WTP.
O
0
10
2024
2025
2
Delay in work & Non deduction of compensation of Rs. 28.07 crore levied on a/c of EOT
O
0
11
2024
2025
3
Huge Deposit from contractor.
O
0
12
2024
2025
4
Slow Progress of work and escalation of cost.
O
0
13
2024
2025
5
Non deduction of performance security
O
0
14
2024
2025
6
Non submission of Work Program Schedule (Bar chart and PERT chart)
O
0
15
2024
2025
7
Non Production of Records.
O
0
*
NOTE:
'O'- Outstanding Paras.
'R' -Reply submitted by the Department/Units.
'C'- Comment by the Directorate of Audit on reply submitted.