Department :Local Fund Accounts (LFA)- Delhi Jal Board
Sub department:Executive Engineer (SDW)-V, Delhi Jal Board, Ring Road, Andrews Ganj, New Delhi-110049
S No. Start Year End Year Para No. Sub Para Subject Status* Outstanding Amount (in Rs.)
1 2023 2024 6 Non-Deduction of TDS (GST) amounting to ₹2,73,004/- on payment to various vendors. O 273004
2 2023 2024 7 Excess payment on A/C of reimbursement of Employees Provident Fund to the Contractors. O 46026
3 2024 2025 9 Non-Submission of Completion Plan amounting to Rs. 15000/- O 15000
4 2023 2024 3 Excess payment of Non-Productivity Linked Bonus for ₹4,232/-. O 4232
5 2023 2024 4 Non-Maintenance of Cash Book as per R&P Rules. O 0
6 2023 2024 5 Non-hiring of Skilled/Semi/Unskilled Workers without using GeM Portal - ₹2.23 crores. O 0
7 2023 2024 1 Discrepancies in opening/closing balances of Bank Accounts for the F.Y. 2023-24. O 0
8 2023 2024 2 Non adjustment of LTC Advance of ₹67,886/-. O 0
9 2024 2025 10 Execution of work without obtaining Performance Guarantee from the contractor. O 0
10 2024 2025 11 Non-Production of Records O 0
11 2023 2024 8 Discrepancies in Work Order NO. 02 (2021-22) in favour of M/s Rehman Builders Pvt. LTd. O 0
12 2023 2024 9 Non Utilization of allocated budget of ₹30.23 crores. O 0
13 2023 2024 10 Expenditure on advertisements worth ₹3.45 lakhs. O 0
14 2023 2024 11 Non-production of records/information. O 0
15 2022 2023 1 Discrepancies in executions of agreements O 0
16 2022 2023 2 Non observation of T&C of letter of intent/contract agreement O 0
17 2022 2023 3 shortcomings in making payment to the contractor O 0
18 2022 2023 4 Non observation of codal provision of GFR-Splitting of works O 0
19 2022 2023 5 Loss due to not availing 15% rebate on advertisement O 0
20 2022 2023 6 Shortcomings in preparation of estimates O 0
21 2022 2023 7 Deployment of skilled/unskilled workers without using GeM portal of Rs.1.71 Crores O 0
22 2022 2023 8 Non Submission of completion plan O 0
23 2022 2023 9 Improper maintenance of Receipt Records O 0
24 2022 2023 10 NPR O 0
25 2024 2025 1 Award of work at abnormally below the Estimated cost. O 0
26 2024 2025 2 Reconciliation of balance in the Bank Account for the F.Y. 2024-25 O 0
27 2024 2025 3 Non-Utilization of Funds to the tune of Rs. 2757.37 lakhs. O 0
28 2024 2025 4 Deployment of Skilled/Unskilled Workers and Purchase of items without using GeM portal O 0
29 2024 2025 5 Irregularities in the deployment of Contractual Staff vide Work Order No. 22 dt. 31.7.24 O 0
30 2024 2025 6 1 (A) Irregularities in the award of work vide Work Order No. 17 dt. 18.7.24. O 0
31 2024 2025 6 2 (B) (A) Irregularities in the award of work vide Work Order No. 31 dt. 31.7.24. O 0
32 2024 2025 7 Discrepancies in the Award of Tender. O 0
33 2024 2025 8 Non-Compliance with Labour Rule & Regulation and Non-Availability of Insurance Certificate. O 0
* NOTE:
'O'- Outstanding Paras.
'R' -Reply submitted by the Department/Units.
'C'- Comment by the Directorate of Audit on reply submitted.