S No. Start Year End Year Para No. Sub Para Subject Status* Outstanding Amount (in Rs.)
1 2003 2007 2 Undue favour to the contractor to the extent of Rs. 91.39 Lakhs. O 0
2 2003 2007 4 Short Recovery of cess amounting Rs. 22.55 Lakhs towards Labour Welfare Fund O 0
3 2003 2007 6 Short Recovery of Income Tax from the officials. O 4180
4 2003 2007 7 Un-authorized expenditure amounting Rs. 9.91 Lakhs O 0
5 2008 2010 2 Revised Technical Sanction O 0
6 2008 2010 3 Execution of huge work at market rates O 0
7 2008 2010 7 Splitting up the work O 0
8 2008 2010 9 Un-cashed Cheques O 0
9 2008 2010 10 Non-production of Records O 0
10 2013 2016 1 Short/Non Recovery of DVAT amounting to Rs. 28354/- O 28354
11 2013 2016 2 Irregularities in award of tender O 0
12 2013 2016 3 Irregularities in execution of works orders O 0
13 2013 2016 6 Time Barred Cheques O 0
14 2016 2019 1 Non observance of condition of quality assurance of the work and making payment of Rs. 1005360/- O 0
15 2019 2023 1 Escalation in cost of works due to Unrealistic Estimates O 0
16 2019 2023 2 Non settlement of Public Works (Suspense) Deposits O 0
17 2019 2023 3 Non settlement of amount under CSSA Rs. 4,33,81,073/- O 0
18 2019 2023 4 Improper booking of office expenditure-Charged to works there of O 0
19 2019 2023 5 Abnormal delay in completion of works beond the stipulated date of completion O 0
20 2019 2023 6 Unfruitful expenditure of Rs. 55,39,26,082/- and loss to govt. for non completion of work O 0