List of Para (Order by Audited Year & Para)
  View Detailed Audit Report
Department :Public Works (PWD)
Sub department:(B-122) Health Project Edu Project Div-I & III ( B-122), Vikas Bhawan, Metcalf House, (1426/12)
S No. Start Year End Year Para No. Sub Para Subject Status* Outstanding Amount (in Rs.)
1 2009 2012 1 Deviation in Technical Sanction O 0
2 2009 2012 2 Irregularities / Shortcoming in the execution of works O 646800
3 2009 2012 3 Variation in Rate & Quantity of items in works O 48485
4 2009 2012 4 Non-surrender of Excess Budget O 0
5 2009 2012 5 Excess Expenditure O 0
6 2009 2012 6 Time Barred cheques amounting to Rs. 1193310/- O 0
7 2012 2018 1 Non compliance of terms and conditions of contract while allowing extra items O 0
8 2012 2018 2 Irregularities in Grant of Extension of time O 0
9 2012 2018 3 Irrgularities in issue of supply/work orders O 0
10 2012 2018 4 Non market survey for procuring items not covered under schedule of rates O 0
11 2018 2020 3 Non revision of technical sanction O 0
12 2018 2020 6 Slow progress of works leading to missing the deadlines for completion of work O 0
13 2018 2020 7 Non revision of technical sanction O 0
14 2018 2020 8 Payment of final bill without obtaining approval of deviation and extra item O 0
15 2018 2020 9 Non deduction of TDS on GST O 97177
16 2020 2023 1 Non recovery of Rs. 2.55 Lakhs from the contractor for failure to provide an Engineer at site O 255000
17 2020 2023 2 Non charging of GST @ 2% on Vendor/Supplier/Contractor Bills O 42692
18 2020 2023 3 Non deduction of the amount of Labour Cess O 10451
19 2020 2023 4 Non recovery of TDS from agencies O 7863
20 2020 2023 5 1 (A) Un-fruitful expenditure amounting to Rs. 2383877/- due to foreclosure of works O 0
21 2020 2023 5 2 (B) Loss of Govt. Infrastructure due foreclosure of works O 0
22 2020 2023 8 Withheld the amount for non-approval of Extension of Time O 0
23 2020 2023 9 Non completion of Projects O 0
24 2020 2023 10 Non Revision of Technical Sanction O 0
25 2020 2023 11 Non compliance of codal formalities laid donw in Works Manual O 0
26 2020 2023 12 Amount withheld on account for minor defects O 0
27 2020 2023 13 Irregular contingent expenditure made by the Division and charged to works O 0
28 2023 2025 1 Non-recovery of Rs. 135000/- from the contractor for failure to provide an Engineer at site O 135000
29 2023 2025 2 Outstanding PWD Deposits amounting to Rs. 20.82 Crores. O 0
30 2023 2025 3 Irregularities on the work "EOR to Distt. Court Rohini Sector-14, Delhi" O 2500000
31 2023 2025 4 Irregular payment to Outsourcing Staff amounting to Rs. 5415859/- O 0
32 2023 2025 5 Non release of Performance Guarantee. O 0
33 2023 2025 6 Loss of Govt. Infrastructure due foreclosure of works. O 0
34 2023 2025 7 Non completion of work. O 0
35 2023 2025 8 Pending Court Cases. O 0
36 2023 2025 9 Non Completion of projects.(Blockage of funds amounting to Rs. 10.19 Crore) O 0
37 2023 2025 10 Non-Production of Records. O 0
* NOTE:
'O'- Outstanding Paras.
'R' -Reply submitted by the Department/Units.
'C'- Comment by the Directorate of Audit on reply submitted.