Webstyle produced NavBar
List of Para (Order by Audited Year & Para)
  View Detailed Audit Report
Department :Public Works (PWD)
Sub department:(M-212) EE (C ) PWD (East) Roads Maintenance Division M-212 (No. XXX), Ramesh Park, Delhi (1902/12)
S No. Start Year End Year Para No. Sub Para Subject Status* Outstanding Amount (in Rs.)
1 2006 2008 1 (a) Irregularities in the work O 0
2 2006 2008 1 (1)(b) Deviation in Technical Sanction O 0
3 2006 2008 2 Engagement of staff for security without approval of the competent authority and irregular booking of expenditure thereof O 0
4 2006 2008 4 Non-observation of CPWD Works manual in respect of annual limit of work order O 0
5 2006 2008 5 Execution of huge number of works on work order basis O 0
6 2006 2008 6 Non-observance of Economy Instruction Issued by the Finance Department O 0
7 2006 2008 7 Unjustified payment to consultant O 0
8 2006 2008 8 Excess payment of Rs. 15405/- made on account of reimbursement of conveyance charges O 0
9 2006 2008 9 Irregular payment of Rs. 49487/- towards conveyance hire O 0
10 2008 2010 1 Irregular payment of Rs. 212129/- on vehicle no. DL 7C E8847 O 0
11 2008 2010 2 Time limit for publicity of tenders O 0
12 2008 2010 3 Irregular expenditure of Rs. 167714/- on the arrangement of tractor trolley O 0
13 2008 2010 4 Irregular purchase of digital camera amounting to Rs. 20133 O 0
14 2008 2010 5 Huge variation between estimate and tendered amount O 0
15 2008 2010 7 Irregular expenditure to the tune of Rs. 661995/- (A/R & M/O Lok Nayak Setu) O 0
16 2008 2010 8 Purchase of computer O 0
17 2008 2010 9 Photocopy bills O 0
18 2008 2010 10 Purchase of computer consumable in violation of the provisions of general financial powers O 0
19 2008 2010 11 Petty sanctions O 0
20 2008 2010 12 Rubber stamps O 0
21 2008 2010 13 Purchase of stationery items O 0
22 2008 2010 14 Irregular sanction of GPF Advance O 0
23 2010 2017 3 Discrepancies observed in the work executed in CRMD M-212 O 92600
24 2010 2017 4 Irregularities in respect of contingency expenditure charge under work head O 0
25 2017 2019 5 Violation of clause 36 under CPWD Manual 2014 i.e. deployment of Graduate Engineer O 0
26 2019 2023 2 Public Works (Suspense) Deposit O 0
27 2019 2023 3 Delay in completion of work beyond the stipulated date of completion O 0
28 2019 2023 4 Office expenditure charged to works O 0
29 2019 2023 5 Unfruitful expenditure due to Foreclosure of contract/abandonment or reduction in scope O 0
30 2023 2025 1 Public works-Civil Deposits O 0
31 2023 2025 2 Award of work on a below rates in comparison to the Estimated Cost O 0
32 2023 2025 3 Office expenditure charged to work O 0
33 2023 2025 4 Non revalidation/release of FDR/Bank Guarantees O 0
34 2023 2024 5 Performance/output of the Division O 0
35 2023 2025 6 Non Maintenance of Contractor Ledger O 0
36 2023 2025 7 Slow progress of works leading to missing the deadlines for completion of work O 0
37 2023 2025 8 Inadmissible payment in violation of the provisions of CPWD Mannual O 0
38 2023 2025 9 NPR O 0
* NOTE:
'O'- Outstanding Paras.
'R' -Reply submitted by the Department/Units.
'C'- Comment by the Directorate of Audit on reply submitted.